Schedule a Time and Meter Based Recurrence

To define a schedule based on a combination of time and meter based recurrence (whichever occurs first):

  1. Access the Schedule Sub-tab.

  2. Select the Time Based and Meter Based Schedule (whichever hits first) option button.

  3. Select the appropriate time-based recurrence.

    • Daily indicates that work orders should be generated every day or every "x" days.

    • Weekly indicates that work orders should be generated weekly, on a given day (or days) of the week. This option allows you to set the day (or days) of the week.

    • Monthly indicates that work orders should be generated monthly or every "x" months. This option also allows you to specify the day or date of the month, such as the 15th of the month or the second Monday.

    • Yearly indicates that work orders should be generated every "x" years. This option also allows you to specify the specific date.

  4. Select the appropriate meter-based recurrence.

  5. If start / end parameters need to be defined or modified, access the Start / End Sub-tab.

  6. Click the Save button.